Construction adjudication: a binding decision on a payment dispute in 28 days
Under section 108 of the Construction Act, either party to a construction contract can refer a dispute to adjudication at any time and get a decision within 28 days. How it works, who it covers and the right to suspend work.
By the Nemexio team · · 5 min read
A right written into every construction contract
Section 108 of the Construction Act gives each party to a construction contract the right to refer a dispute arising under it to adjudication [1]. The contract must allow notice to be given at any time, secure the appointment of the adjudicator and the referral within 7 days of that notice, and require a decision within 28 days of the referral [1].
The 28 days can be extended by 14 days with the consent of the party who referred the dispute, or for longer if both parties agree. The adjudicator must act impartially and may take the initiative in finding out the facts and the law [1]. If a contract does not meet these requirements, the adjudication rules of the Scheme for Construction Contracts apply instead [2].
Binding now, final later
An adjudicator's decision is binding until the dispute is finally settled by legal proceedings, arbitration or agreement [1]. In practice this means the losing party has to comply now and argue later — which is why adjudication is the usual way an unpaid notified sum gets paid.
Which contracts are covered
The Act applies to contracts for construction operations. It does not apply to a contract with a residential occupier — work on a house or flat that the client lives in, or intends to live in [4]. Disputes with homeowners therefore follow the ordinary routes, such as the small claims court, rather than statutory adjudication.
Suspending work for non-payment
If a sum due is not paid in full by the final date for payment and no valid Pay Less Notice has been given, section 112 allows you to suspend all or part of your work [3]. You must first give at least 7 days' notice of your intention to suspend, stating the grounds [3].
You are entitled to your reasonable costs and expenses caused by the suspension, and the period of suspension is added to the time allowed for completion [3].
Preparing a strong referral
- The contract and its payment clauses — or confirmation that the Scheme applies.
- Your application for payment and the date you submitted it.
- Any Payment Notice or Pay Less Notice you received, with its date.
- Every reminder and piece of correspondence, with dates.
- A clear calculation of the sum claimed, with any interest shown separately.
Nemexio keeps this timeline for every line automatically — application date, statutory deadlines and each reminder sent — so the chronology is ready if a dispute goes further. Adjudication has costs and consequences, so take independent advice before you refer a dispute.
Put this into practice
Sources
- [1]legislation.gov.uk — Housing Grants, Construction and Regeneration Act 1996, section 108 — Right to refer disputes to adjudication
- [2]legislation.gov.uk — The Scheme for Construction Contracts (England and Wales) Regulations 1998
- [3]legislation.gov.uk — Housing Grants, Construction and Regeneration Act 1996, section 112 — Right to suspend performance for non-payment
- [4]legislation.gov.uk — Housing Grants, Construction and Regeneration Act 1996, section 106 — Provisions not applicable to contract with residential occupier
Sources checked on 25 September 2026. This article is general information, not legal advice. For a specific contract or dispute, take independent advice.