Construction Act

Payment Notices and Pay Less Notices: the Construction Act deadlines that decide who gets paid

How the Construction Act Payment Notice (5 days) and Pay Less Notice (7 days) deadlines work, what happens when a payer misses them, and how the notified sum becomes payable in full.

By the Nemexio team · · 6 min read

Why notices matter more than invoices

In UK construction, how much has to be paid is often settled not by the quality of the work but by whether the right notice was served on time. Part II of the Housing Grants, Construction and Regeneration Act 1996 — the Construction Act — sets a sequence of notices that every construction contract must follow, either through its own wording or, where the contract is silent, through the statutory Scheme for Construction Contracts [1][3].

Step 1: the payment due date and the Payment Notice

Each interim payment has a payment due date. Under section 110A, the payer — or a person named in the contract, such as the contract administrator — must give a Payment Notice no later than five days after that date [1].

The notice must state the sum the payer considers due and the basis on which it has been calculated [1]. A bare figure with no explanation does not meet that requirement.

What if no Payment Notice arrives?

The sum does not become open to negotiation. Where the contract requires you to submit an application for payment before the due date — as most interim valuation clauses do — your application stands in default as the notice of the sum due [2].

Where it does not, you can serve your own payee's notice in default. The final date for payment is then pushed back by the number of days your notice was late [2].

Step 2: the Pay Less Notice

Section 111 requires the payer to pay the notified sum on or before the final date for payment [4]. The only way to pay less is a Pay Less Notice, served no later than the prescribed period before the final date, setting out the sum the payer considers due and how it was calculated [4].

Where the contract does not set its own periods, the Scheme fixes the final date for payment at 17 days after the due date and the prescribed period for a Pay Less Notice at 7 days [3]. The Commercial Payments Bill, introduced on 19 May 2026, would write the 7-day Pay Less requirement directly into the Act [5].

A worked timeline under the Scheme

  • Day 0 — payment due date.
  • Day 5 — last day for the payer's Payment Notice.
  • Day 10 — last day for a Pay Less Notice (7 days before the final date).
  • Day 17 — final date for payment.

JCT, NEC and bespoke contracts often set their own periods. The Scheme only fills the gaps, so always check the payment clause first.

Using the position in a reminder

When a deadline has been missed, a reminder does not need to be aggressive. It only needs to state the facts: the date of the application, the notice that was not received, and the statutory basis. That is a very different letter from a polite nudge — and much harder to ignore.

Nemexio works out these dates from the application date on every line, flags a notified sum automatically and puts the position in plain words in each reminder.

Put this into practice

Sources

  1. [1]legislation.gov.uk — Housing Grants, Construction and Regeneration Act 1996, section 110A — Payment notices
  2. [2]legislation.gov.uk — Housing Grants, Construction and Regeneration Act 1996, section 110B — Payee's notice in default
  3. [3]legislation.gov.uk — The Scheme for Construction Contracts (England and Wales) Regulations 1998
  4. [4]legislation.gov.uk — Housing Grants, Construction and Regeneration Act 1996, section 111 — Requirement to pay notified sum
  5. [5]Dentons — The proposed retention ban and other new payment legislation (UK construction focus), 2 June 2026

Sources checked on 25 September 2026. This article is general information, not legal advice. For a specific contract or dispute, take independent advice.