The construction retention ban: what the Commercial Payments Bill means for your retentions

The UK government plans to ban cash retentions in construction contracts. What the Commercial Payments Bill proposes, the transition period, the likely timeline and what to do with retentions held today.

By the Nemexio team · · 6 min read

What a retention is — and why it is going

A retention is a percentage of each payment withheld by the payer as security against defects, usually released in stages once the work is complete and the defects period has ended.

Responses to the government's consultation showed broad agreement that retained money is often subject to unjustified late, partial and non-payment [1], and that it can be lost entirely when a firm higher up the chain becomes insolvent [3]. The issue is not new: the government had already reviewed retentions in 2017 [5].

From consultation to Bill

The late payment consultation ran from 31 July to 23 October 2025 and put forward two options for retentions: an outright ban, or a requirement to hold retentions in protected third-party accounts [3].

In its response the government chose the ban, noting it was seen as simpler for industry to implement and easier to enforce [1]. The Commercial Payments Bill [HL] was introduced into Parliament on 19 May 2026 — referred to in the government's press release as the Small Business Protections Bill [2].

What the Bill proposes

  • A ban on contract terms that allow retention sums to be deducted and withheld under a construction contract [2].
  • A transition period for retention clauses agreed in the two years before the ban comes into force, with any remaining retention to be returned before the end of that period [2].
  • An implied fixed sum payable to the supplier for any unauthorised deduction of retention, on top of statutory interest and compensation [2].
  • A requirement written into the Act for any Pay Less Notice to be given no later than 7 days before the final date for payment [2].

When will it apply?

No commencement date has been announced. The reforms are expected to take effect no earlier than 2027, depending on the parliamentary timetable [4], and the government has said it will consult on how the ban will be implemented [3].

Commentators have raised practical questions, including the cost and availability of alternative forms of security, such as bonds, and possible workarounds through payment scheduling [3].

What to do with the retentions you hold today

  • Record every retention with its amount, the contract it belongs to and its release date or dates.
  • Diary the end of each defects liability period and ask for release on the day it falls due.
  • Keep the evidence together: the practical completion certificate, the certificate of making good and any defects correspondence.
  • Check contracts you sign from now on — retention clauses agreed in the run-up to the ban may fall within the transition rules.

Nemexio keeps retentions in their own register with a release date countdown, so they are never mixed up with ordinary overdue invoices.

Put this into practice

Sources

  1. [1]GOV.UK — Late payment consultation: time to pay up — government response
  2. [2]Dentons — The proposed retention ban and other new payment legislation (UK construction focus), 2 June 2026
  3. [3]Osborne Clarke — UK government to ban construction retentions and tighten late payment rules
  4. [4]Farrer & Co — The government's late payment reforms: a practical guide for businesses, May 2026
  5. [5]GOV.UK — Retention payments in the construction industry — consultation

Sources checked on 25 September 2026. This article is general information, not legal advice. For a specific contract or dispute, take independent advice.